Farmfoods

Location: Cumbernauld, Glasgow
Crushing Deconstruction

This project involved the demolition of 12nr portal frame sheds and the breaking up and crushing of slab throughout the site.

The scope of work also included the removal of the asbestos cement sheets under a controlled wet and drop procedure. This involved 3 in-sync excavators pulling simultaneously to create the controlled drop. It's always impressive to see, check out the video to view!

The project was successfully completed on time and within budget, to the satisfaction of the client.

Value
£245,000
Recycling rate
98.4%
Waste
1050 ton
Man hours
4320
Get in touch