Project

HMP Deerbolt – MOJ

Location: Durham

The Hookstone Group, acting as Principal Contractor, successfully delivered machine-led demolition and piling mat installation at the HMP Deerbolt site in Barnard Castle. The project, valued at £250,000, was completed over an eight-week period.

The works involved the controlled demolition of existing structures using advanced machinery, followed by the installation of robust piling mats to provide a safe and stable platform for subsequent construction activities. Our team ensured that all works were executed efficiently while maintaining the highest standards of safety and compliance, particularly within a secure correctional facility environment.

Through careful planning, expert machine operation, and seamless on-site coordination, the project was delivered on time and to specification, showcasing Hookstone Group’s expertise in combining demolition and groundwork solutions in challenging environments.

Value
£250,000
Get in touch